LIFamilies.com - Long Island, NY


RSS
Articles Business Directory Blog Real Estate Community Forum Shop My Family Contests

Log In Chat Index Search Rules Lingo Create Account

Quick navigation:   

Another home renovation/dormer question

Posted By Message

Rycois
Blessed with 2blue/2pink

Member since 12/05

13341 total posts

Name:
J

Another home renovation/dormer question

If you had a dormer or big project done, how long before it actually started??

Message edited 5/14/2009 11:06:01 AM.

Posted 5/13/09 11:08 AM
 
Prudential Douglas Elliman Real Estate
Long Island's Largest Bridal Resource
  |   Long Island Weddings

GoldenRod
10 years on LIF!

Member since 11/06

26792 total posts

Name:
Shawn

Re: Another home renovation/dormer question

It took me a year and 3 days between filing the original paperwork with the Town until I finally got my permit..... Chat Icon 2 variance hearings, plus lots of delays.

Once I got the permit, my contractor started within a few days.

We doubled the size of our house. Full basement, and 1500 s/f of space. 2 stories. We dug the foundation in mid-August, and the painter was finished by Thanksgiving, and the carpets were in shortly after, which is when we finally "moved in" to the new rooms.

So, 3 or 4 months for the architect drawings, 1 year for permits, and roughly 4 months to actually build the addition... Chat Icon

Posted 5/13/09 11:21 AM
 

ave1024
I Took The Wrong Road

Member since 12/07

6153 total posts

Name:
That Led To The Wrong Tendencies

Re: Another home renovation/dormer question

Expect it to take time.

The start of the process usually takes 2-3 months to get the permits and blueprints. Then usually 8-12 weeks for construction, but I would expect three months personally. If you are doing a side extension and they need to pour slab, the slab takes 6 weeks to cure by itself.

Posted 5/13/09 11:23 AM
 

Rycois
Blessed with 2blue/2pink

Member since 12/05

13341 total posts

Name:
J

Re: Another home renovation/dormer question

Posted by ave1024

Expect it to take time.

The start of the process usually takes 2-3 months to get the permits and blueprints. Then usually 8-12 weeks for construction, but I would expect three months personally. If you are doing a side extension and they need to pour slab, the slab takes 6 weeks to cure by itself.



Thanks

Message edited 5/14/2009 11:06:57 AM.

Posted 5/13/09 11:25 AM
 

MrsM-6-7-08
<3

Member since 8/06

4249 total posts

Name:
Nicole

Re: Another home renovation/dormer question

It defin takes a long time, mine took longer because of all the wiring my DH did.
So we werent able to close up the walls until that was done.

But we closed in late august 2006, filed with the town, september/october
And i remember we got the call we were approved in march 2007
We didnt get to start the construction til June 2007.

We officially moved in May 2008

Posted 5/13/09 11:28 AM
 

Rycois
Blessed with 2blue/2pink

Member since 12/05

13341 total posts

Name:
J

Re: Another home renovation/dormer question

So I guess my next question is will the contractor hold you to a start date or can you dictate that?
.

Message edited 5/14/2009 11:07:15 AM.

Posted 5/13/09 11:34 AM
 

GoldenRod
10 years on LIF!

Member since 11/06

26792 total posts

Name:
Shawn

Re: Another home renovation/dormer question

Posted by SweetCaroline

So I guess my next question is will the contractor hold you to a start date or can you dictate that?

Like if I they get the go ahead and want to start in October but I want to halt it due to an impending delivery, would they give me a problem? Can I specify in my contract that I have the right put it off? DH thinks this is a problem - I say, if they're getting paid, I don't see why they would care.



Within reason, they work to your schedule. (Certain things, especially concrete related, closing up the house, and timing sub-contractors have to be done in a certain timeframe). As long as you tell them up front, they'll work with you. (or at least they SHOULD.) Mine did.

Posted 5/13/09 1:23 PM
 

Rycois
Blessed with 2blue/2pink

Member since 12/05

13341 total posts

Name:
J

Re: Another home renovation/dormer question

I def. want to get the permits and that stuff going.

Message edited 5/14/2009 11:07:30 AM.

Posted 5/13/09 1:45 PM
 

KLSbear
LIF Adult

Member since 1/06

1908 total posts

Name:
Karen

Re: Another home renovation/dormer question

Permits and architects drawings probably were about 2 months for us. We started the construction on the dormer just after Thanksgiving, and it was finished in early April - 4 months but we had the Christmas holidays which added some delay. We had extensive tile work done in the master bath which easily added a few weeks, and the town required some structural supports added to the basement, so that work added at least another week, maybe 2. One thing that's hard to control is the inspection schedule. Your contractor may have the electrical done, but if the town can't get there for a week you have to wait before they can start sheetrock work.

Posted 5/13/09 2:07 PM
 
 

Potentially Related Topics:

Topic Posted By Started Replies Forum
Is your DH dragging his feet on your home renovation? curliegirl 8/14/07 8 Home
Complete Home Renovation BikerGrl 11/5/06 2 Home
Renewing home insurance and mortgage company question... KPsquared 12/16/05 2 Home
Those who are doing/did home improvements... question... Leeners 11/14/05 12 Home
Question for stay at home Moms........ princess99 10/19/05 9 Parenting
I got my first offer on my co-op - home equity question DjPiLL 9/14/05 19 Home
 
Quick navigation:   
Currently 271052 users on the LIFamilies.com Chat
New Businesses
1 More Rep
Carleton Hall of East Islip
J&A Building Services
LaraMae Health Coaching
Sonic Wellness
Julbaby Photography LLC
Ideal Uniforms
Teresa Geraghty Photography
Camelot Dream Homes
Long Island Wedding Boutique
MB Febus- Rodan & Fields
Camp Harbor
Market America-Shop.com
ACM Basement Waterproofing
Travel Tom

      Follow LIWeddings on Facebook

      Follow LIFamilies on Twitter
Long Island Bridal Shows