Posted By |
Message |
Rycois
Blessed with 2blue/2pink
Member since 12/05 13341 total posts
Name: J
|
Another home renovation/dormer question
If you had a dormer or big project done, how long before it actually started??
Message edited 5/14/2009 11:06:01 AM.
|
Posted 5/13/09 11:08 AM |
|
|
Prudential Douglas Elliman Real Estate
Long Island's Largest Bridal Resource | Long Island Weddings |
GoldenRod
10 years on LIF!
Member since 11/06 26792 total posts
Name: Shawn
|
Re: Another home renovation/dormer question
It took me a year and 3 days between filing the original paperwork with the Town until I finally got my permit..... 2 variance hearings, plus lots of delays.
Once I got the permit, my contractor started within a few days.
We doubled the size of our house. Full basement, and 1500 s/f of space. 2 stories. We dug the foundation in mid-August, and the painter was finished by Thanksgiving, and the carpets were in shortly after, which is when we finally "moved in" to the new rooms.
So, 3 or 4 months for the architect drawings, 1 year for permits, and roughly 4 months to actually build the addition...
|
Posted 5/13/09 11:21 AM |
|
|
ave1024
I Took The Wrong Road
Member since 12/07 6153 total posts
Name: That Led To The Wrong Tendencies
|
Re: Another home renovation/dormer question
Expect it to take time.
The start of the process usually takes 2-3 months to get the permits and blueprints. Then usually 8-12 weeks for construction, but I would expect three months personally. If you are doing a side extension and they need to pour slab, the slab takes 6 weeks to cure by itself.
|
Posted 5/13/09 11:23 AM |
|
|
Rycois
Blessed with 2blue/2pink
Member since 12/05 13341 total posts
Name: J
|
Re: Another home renovation/dormer question
Posted by ave1024
Expect it to take time.
The start of the process usually takes 2-3 months to get the permits and blueprints. Then usually 8-12 weeks for construction, but I would expect three months personally. If you are doing a side extension and they need to pour slab, the slab takes 6 weeks to cure by itself.
Thanks
Message edited 5/14/2009 11:06:57 AM.
|
Posted 5/13/09 11:25 AM |
|
|
MrsM-6-7-08
<3
Member since 8/06 4249 total posts
Name: Nicole
|
Re: Another home renovation/dormer question
It defin takes a long time, mine took longer because of all the wiring my DH did. So we werent able to close up the walls until that was done.
But we closed in late august 2006, filed with the town, september/october And i remember we got the call we were approved in march 2007 We didnt get to start the construction til June 2007.
We officially moved in May 2008
|
Posted 5/13/09 11:28 AM |
|
|
Rycois
Blessed with 2blue/2pink
Member since 12/05 13341 total posts
Name: J
|
Re: Another home renovation/dormer question
So I guess my next question is will the contractor hold you to a start date or can you dictate that? .
Message edited 5/14/2009 11:07:15 AM.
|
Posted 5/13/09 11:34 AM |
|
|
GoldenRod
10 years on LIF!
Member since 11/06 26792 total posts
Name: Shawn
|
Re: Another home renovation/dormer question
Posted by SweetCaroline
So I guess my next question is will the contractor hold you to a start date or can you dictate that?
Like if I they get the go ahead and want to start in October but I want to halt it due to an impending delivery, would they give me a problem? Can I specify in my contract that I have the right put it off? DH thinks this is a problem - I say, if they're getting paid, I don't see why they would care.
Within reason, they work to your schedule. (Certain things, especially concrete related, closing up the house, and timing sub-contractors have to be done in a certain timeframe). As long as you tell them up front, they'll work with you. (or at least they SHOULD.) Mine did.
|
Posted 5/13/09 1:23 PM |
|
|
Rycois
Blessed with 2blue/2pink
Member since 12/05 13341 total posts
Name: J
|
Re: Another home renovation/dormer question
I def. want to get the permits and that stuff going.
Message edited 5/14/2009 11:07:30 AM.
|
Posted 5/13/09 1:45 PM |
|
|
KLSbear
LIF Adult
Member since 1/06 1908 total posts
Name: Karen
|
Re: Another home renovation/dormer question
Permits and architects drawings probably were about 2 months for us. We started the construction on the dormer just after Thanksgiving, and it was finished in early April - 4 months but we had the Christmas holidays which added some delay. We had extensive tile work done in the master bath which easily added a few weeks, and the town required some structural supports added to the basement, so that work added at least another week, maybe 2. One thing that's hard to control is the inspection schedule. Your contractor may have the electrical done, but if the town can't get there for a week you have to wait before they can start sheetrock work.
|
Posted 5/13/09 2:07 PM |
|
|